The exterior framing of 1 Dog Lane(formerly referred to as TS-1) is now complete! Installation of the windows and the interior framing of the apartments have begun. The roof is underway, and the air vapor barrier is being applied to the exterior. In addition to the framing inside, electrical work, plumbing, and HVAC work is underway.
Next door, 9 Dog Lane (formerly DL-1/2) is following a similar schedule and activities are sequenced to track a week after 1 Dog Lane.
1 Dog Lane |
Over at the site of the future parking garage, work is progressing steadily. The footings on the northern end of the building have been poured.