June 8, 2011
June 6, 2011
Demolition Continues
The work on the former Publications building will continue this week. While most of the work to date has been on the interior, work on the exterior will begin soon.
Demolition of 13 and 14 Dog Lane (former Select Physical Therapy and Nayden Health Clinic buildings, respectively) will begin soon. As with the former Publications building, the first steps will be to complete any interior work before anything will be done to the exterior of the building.
And, the University will begin work on its sanitary sewer upgrade next week. The sewer line runs along Storrs Road, but most of the work will be done underground. Traffic in both directions will be maintained, although it may be slower at times to accommodate the work in progress.
Demolition of 13 and 14 Dog Lane (former Select Physical Therapy and Nayden Health Clinic buildings, respectively) will begin soon. As with the former Publications building, the first steps will be to complete any interior work before anything will be done to the exterior of the building.
And, the University will begin work on its sanitary sewer upgrade next week. The sewer line runs along Storrs Road, but most of the work will be done underground. Traffic in both directions will be maintained, although it may be slower at times to accommodate the work in progress.
May 27, 2011
And so it begins. . .
The demolition of the former Publications building has begun. This will be a gradual process, beginning with work on the interior of the building.
May 20, 2011
Demolition Update and Parking News
The Town of Mansfield has selected Standard Demolition Services of Trumbull, CT, to complete the abatement and demolition of the former Publications building [1266 Storrs Road (corner of Dog Lane and Route 195)]. As noted on May 13, the site of the building will be part of Phase 1A of Storrs Center.
In preparation of the anticipated start of demolition, the parking lot behind the building will be closed as of Friday, May 20 at 5:00 pm. All vehicles should be moved after Friday because a fence will soon be installed around the site.
It is anticipated that the Bishop Center parking lots will close on May 26. This lot will close to accommodate construction in that area.
May 13, 2011
Demo to Begin Soon
The Town of Mansfield expects the demolition of the former Publications building, located on the corner of Dog Lane and Storrs Road (Route 195), to begin soon after May 23. Final permits and approvals are in the works.
Once the building has been demolished, construction of the first phase of Mansfield's new downtown, Storrs Center, can begin. Plans for the first phase include the realignment of Dog Lane and the construction of a mixed-use building which will house commercial uses on the ground level and residential units on the upper floors.
For more details, please visit the Mansfield Downtown Partnership's website: www.mansfieldct.org/mdp.
Once the building has been demolished, construction of the first phase of Mansfield's new downtown, Storrs Center, can begin. Plans for the first phase include the realignment of Dog Lane and the construction of a mixed-use building which will house commercial uses on the ground level and residential units on the upper floors.
For more details, please visit the Mansfield Downtown Partnership's website: www.mansfieldct.org/mdp.