April 16, 2012

Reaching the Top

The final piece of pre-cast for the parking garage has been installed.  The large crane will be dismantled and will leave the site.  The focus for the garage will now be completing the mechanical and electrical components for the scheduled August opening.

Workers guide the final pre-cast piece into place.



This crane's work is done.


 
Meanwhile, the work on 1 Dog Lane and 9 Dog Lane continues.  The interior spaces are progressing as are the exterior finishes, including the first floor commercial spaces.

The utilities work on Dog Lane is on-going.  The street remains closed to through traffic during the day, and local traffic is restricted to alternating one lane to accommodate the work.

The facades of 1 Dog Lane and 9 Dog Lane are taking shape, while the utilities work on Dog Lane continues.  In the background, UConn's School of Fine Arts and South Campus are visible.